Niepe Construction was contracted by RoadTek to assist with the construction of four headwalls in the Lockyer Valley. The works revolved around two existing pipe crossings under the Warrego Highway that consisted of twin 2300mm diameter concrete pipes.
Our work in this project includes
- Detailed Excavation of toe walls
- Installation of Reinforcing
- Erection of Formwork
- Placement of Structural Concrete
- Form, Reo and Pour of concrete lined drains
- Backfill to Concrete structures
- Landscaping of completed works
- Installation of fencing