Gateway Upgrade Project
(August 2007 – June 2012)
Involved in the construction of various structures within the southern section of the works including CROP railway bridge, Wynnum Road Bridge, Old Cleveland Road Bridge and a number of associated works including in situ barriers, gantry bases and RC retaining walls. The works on the southern section involved a number of green field structures and widening of existing structures which required flexibility in work hours and shifts to meet the requirements of the project deed.
Works also included set up of various site compounds including concrete slabs and shed and awning installation.